Skip to content

Test Fixture Fulfillment Process

This document outlines the complete fulfillment process for designing, manufacturing, and delivering bed-of-nails test fixtures to our customers.

Process Overview

Detailed Process Steps

1. Pre-Kickoff

After a Purchase Order (PO) is submitted, the pre-kickoff phase ensures we have all the necessary information and customer approval before starting the project.

Activities:

  • Immediate Follow-up: Upon receiving a PO, we send a summary email to the customer containing:

    • Complete fixture configuration details
    • List of design files we will be using (PCB files, specifications, etc.)
    • File format confirmation (ODB++, IPC-2581, or Gerber)
    • Any special requirements or customizations
  • Customer Review & Confirmation: The customer must review and confirm that:

    • The fixture configuration matches their requirements
    • We have the correct and most current design files
    • All specifications are accurate
  • Project Scheduling: Once confirmation is received, the project will be scheduled to start on the following Monday.

Timeline: Immediate follow-up after PO; awaiting customer confirmation

Key Stakeholders: Sales team, Customer, Project Manager


2. Kickoff

Project kickoffs are scheduled for Mondays to ensure a full week of productivity.

Activities:

  • Project Planning:

    • Engineering project is fully planned
    • All tasks are created and assigned
    • Timeline and milestones are established
    • Resources are allocated
  • Kickoff Email: A comprehensive kickoff email is sent to the customer containing:

    • Project Lead: Name and contact information of the dedicated project lead
    • Engineering Resources: Team members dedicated to the project and their roles
    • Project Timeline: Estimated completion dates for each phase
    • Communication Plan: How and when updates will be provided
    • Next Steps: What to expect in the design phase

Timeline: Monday following customer confirmation

Key Stakeholders: Project Manager, Engineering Team, Customer


3. Design Phase

The engineering team develops the test fixture design based on the confirmed PCB files and specifications.

Activities:

  • PCB Analysis: Import and analyze the customer's PCB design files
  • Test Point Identification: Identify all test points and net connections
  • Fixture Layout: Design the mechanical fixture layout including:
    • Probe placement and alignment
    • PCB mounting and support structures
    • Connector and interface locations
    • Vacuum or mechanical hold-down systems
  • Electrical Design: Create wiring diagrams and electrical connections
  • Component Selection: Select appropriate probes, connectors, and hardware
  • Documentation: Generate design documentation and CAD files

Timeline: Varies based on fixture complexity (typically 1-3 weeks)

Key Stakeholders: Design Engineers, Project Lead

Deliverables:

  • 3D CAD models
  • Mechanical drawings
  • Electrical schematics
  • Bill of Materials (BOM)
  • Probe list and specifications

4. Design Review

The completed design is reviewed with the customer to ensure it meets all requirements before manufacturing.

Activities:

  • Design Package Preparation: Compile all design documentation including:

    • 3D renderings and CAD models
    • Technical drawings
    • Probe layout diagrams
    • BOM and specifications
  • Customer Presentation: Present the design to the customer, highlighting:

    • Test coverage and probe placement
    • Fixture features and functionality
    • Any deviations from standard design
    • Timeline for manufacturing
  • Feedback & Revisions:

    • Address customer questions and concerns
    • Implement any requested changes
    • Obtain formal design approval

Timeline: 3-5 business days for review; additional time if revisions are needed

Key Stakeholders: Project Lead, Design Engineers, Customer

Deliverables:

  • Complete design package
  • Customer approval sign-off

5. Manufacturing

Once the design is approved, the fixture enters the manufacturing phase.

Activities:

  • Material Procurement: Order all components, probes, and materials per the BOM

  • Mechanical Fabrication:

    • CNC machining of fixture plates and components
    • Surface finishing and treatment
    • Quality inspection of machined parts
  • Assembly:

    • Install probes and receptacles
    • Wire electrical connections
    • Mount connectors and interfaces
    • Assemble mechanical components
  • Integration: Combine all subsystems into the complete fixture

Timeline: 2-4 weeks depending on complexity and component lead times

Key Stakeholders: Manufacturing Team, Procurement, Project Lead

Deliverables:

  • Completed physical fixture
  • Manufacturing documentation
  • Assembly verification checklist

6. Quality Assurance

Every fixture undergoes rigorous quality assurance testing before shipment.

Activities:

  • Visual Inspection:

    • Check for manufacturing defects
    • Verify proper assembly
    • Confirm component placement
  • Electrical Testing:

    • Continuity testing of all test points
    • Resistance measurements
    • Short circuit detection
    • Signal integrity verification
  • Functional Testing:

    • Test with actual PCB (if available) or test board
    • Verify all test points are accessible
    • Check mechanical alignment and fit
    • Validate connector interfaces
  • Documentation:

    • Complete QA test reports
    • Photograph fixture for records
    • Create calibration certificates if applicable

Timeline: 1-3 business days

Key Stakeholders: QA Team, Test Engineers, Project Lead

Deliverables:

  • QA test report
  • Fixture certification
  • Calibration certificates (if applicable)

7. Shipping

The completed and tested fixture is carefully packaged and shipped to the customer.

Activities:

  • Packaging:

    • Protective packaging of the fixture
    • Include all accessories and documentation
    • Add handling instructions
  • Documentation Package:

    • User manual and operation guide
    • Maintenance instructions
    • Wiring diagrams and schematics
    • QA test reports
    • Calibration certificates
    • Spare parts list
  • Logistics:

    • Coordinate shipping method with customer
    • Arrange pickup with carrier
    • Provide tracking information
    • Insurance coverage
  • Customer Notification:

    • Send shipping confirmation email
    • Provide tracking number
    • Include expected delivery date
    • Schedule follow-up for receipt confirmation

Timeline: 1-2 business days after QA approval

Key Stakeholders: Shipping Coordinator, Project Lead, Customer

Deliverables:

  • Packaged fixture
  • Complete documentation package
  • Tracking information
  • Delivery confirmation

Communication & Support

Throughout the entire fulfillment process:

  • Regular Updates: Customers receive weekly status updates via email
  • Issue Escalation: Any delays or issues are communicated immediately
  • Point of Contact: The assigned Project Lead is available for questions throughout the process
  • Post-Delivery Support: Technical support is provided after delivery for setup and initial use

Timeline Summary

PhaseTypical Duration
Pre-Kickoff1-3 business days (awaiting customer confirmation)
Kickoff1 day (Monday)
Design1-3 weeks
Design Review3-5 business days
Manufacturing2-4 weeks
Quality Assurance1-3 business days
Shipping1-2 business days + transit time
Total6-10 weeks from PO to delivery

Note: Timeline may vary based on fixture complexity, component availability, and customer responsiveness.